Jasper, Illinois is served through the MISO market (Midcontinent Independent System Operator), and the figures below describe the public grid around a prospective data center site there. Jasper carries 17 mapped substations within its boundary, and the highest reachable grid access is 345 kV. Service in Jasper spans 5 utilities, with AMEREN ILLINOIS COMPANY, CITY OF NEWTON - (IL), CLAY ELECTRIC COOP INC among those mapped.
Grid position at a glance
- Serving utilities
- AMEREN ILLINOIS COMPANY, CITY OF NEWTON - (IL), CLAY ELECTRIC COOP INC, NORRIS ELECTRIC COOP, SOUTHWESTERN ELECTRIC COOP INC - (IL)
- ISO / market
- MISO (Midcontinent Independent System Operator)
- Highest grid access
- 345 kV
- Substations in county
- 17
- Industrial retail rate
- 10.1¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 3 of 5 serving utilities: 1.6 to 15.2¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- 10 projects, 1,484 MW
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 982 lb CO2/MWh
- Water withdrawals
- 466 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 19,428 employed in construction within ~120 km (36 of 38 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Jasper
The material below frames Jasper, Illinois for a prospective large load, drawing only on public sources. Grid access in Jasper extends to 345 kV, a high-voltage line class. The mapped layer places 17 substations across Jasper, a moderate density.
Interconnection over Jasper runs through the MISO market (Midcontinent Independent System Operator) and its rules. For Jasper, the rate shown is the state industrial average of 10.1 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Jasper that report an industrial rate span 3 of 5 serving utilities: 1.6 to 15.2¢/kWh, shown as context and never as the county rate.
The queue feeds show 10 projects for Jasper, totalling 1,483.8 MW of requested capacity. Nothing is on file for Jasper, Illinois in EIA-860M as planned or under construction, which counts as a measured zero. Jasper sits under a balancing authority that eGRID puts at 981.982 lb CO2 per MWh.
Jasper withdrew 465.51 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 19,428 people are employed in construction within a 120 km commute of Jasper (BLS QCEW), which frames staffing distance rather than free labour.
For Jasper, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Jasper, Illinois describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Jasper, Illinois, a specific address needs its own interconnection study, which this page does not attempt. The figures for Jasper, Illinois refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.