Hancock, IL: data center power outlook
For Hancock, Illinois, the public grid picture begins with its place in the MISO market (Midcontinent Independent System Operator) and the infrastructure mapped inside the county. Grid access across Hancock tops out at 161 kV, over a footprint of 20 mapped substations. In Hancock, 8 utilities share the retail territory, among them ACCESS ENERGY COOP, ADAMS ELECTRIC COOP, AMEREN ILLINOIS COMPANY.
Grid position at a glance
- Serving utilities
- ACCESS ENERGY COOP, ADAMS ELECTRIC COOP, AMEREN ILLINOIS COMPANY, INTERSTATE POWER AND LIGHT CO, LEWIS COUNTY RURAL E C A, MCDONOUGH POWER COOP, UNION ELECTRIC CO - (MO), WESTERN ILLINOIS ELEC COOP
- ISO / market
- MISO (Midcontinent Independent System Operator)
- Highest grid access
- 161 kV
- Substations in county
- 20
- Industrial retail rate
- 10.1¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 1 of 8 serving utilities: 1.6¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- 2 projects, 152 MW
- Proposed generation
- 3 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 982 lb CO2/MWh
- Water withdrawals
- 3.3 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 9,625 employed in construction within ~120 km (31 of 33 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Hancock
This page gathers the public grid evidence for Hancock, Illinois that bears on a large new load. The strongest mapped access in Hancock is 161 kV, squarely transmission class. Hancock carries 20 substations in the mapped layer, spread across the county.
For Hancock, the MISO market (Midcontinent Independent System Operator) is the operator that handles interconnection and capacity. The state industrial average retail rate is 10.1 cents per kWh, drawn from EIA-861 and applied to Hancock at the state level rather than as a county rate. The serving utilities in Hancock that publish a rate range 1 of 8 serving utilities: 1.6¢/kWh, a spread kept separate from the state average.
On record for Hancock are 2 interconnection-queue projects, totalling 152 MW of requested capacity. Federal filings (EIA-860M) list 2.5 MW of generation as planned or under construction in Hancock. Grid carbon intensity for Hancock, via its balancing authority, is 981.982 lb CO2 per MWh in eGRID.
USGS 2015 puts freshwater withdrawals across Hancock at 3.26 million gallons per day for all uses, a measure of use, not spare supply. Within roughly a 120 km commute of Hancock, about 9,625 people are employed in construction (BLS QCEW), which speaks to how far crews for a multi-year build would travel, not to labour known to be free.
Read the Hancock figures as screening-grade context: they describe the surrounding grid, not a specific parcel. The numbers for Hancock, Illinois qualify one another, so grid access, substation density, market membership, and rate are meant to be read as a set, not in isolation. Past this screening view, siting in Hancock, Illinois turns on a study of a particular address, something no county-level page can stand in for. Every number shown for Hancock, Illinois traces to a public source listed below, with its retrieval date, so the provenance is auditable rather than asserted.