Power by county

Coles, IL: data center power outlook

The grid around Coles, Illinois is summarized here from public data, starting from the county's position in the MISO market (Midcontinent Independent System Operator). Inside Coles the mapped layer shows 34 mapped substations, with grid access reaching 345 kV at its strongest point. Retail service across Coles is split among 6 utilities, among them AMEREN ILLINOIS COMPANY, COLES-MOULTRIE ELECTRIC COOP, ENERSTAR POWER CORP.

Grid position at a glance

Serving utilities
AMEREN ILLINOIS COMPANY, COLES-MOULTRIE ELECTRIC COOP, ENERSTAR POWER CORP, NORRIS ELECTRIC COOP, SHELBY ELECTRIC COOP, INC, SOUTHWESTERN ELECTRIC COOP INC - (IL)
ISO / market
MISO (Midcontinent Independent System Operator)
Highest grid access
345 kV
Substations in county
34
Industrial retail rate
10.1¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
5 of 6 serving utilities: 1.6 to 15.2¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
12 projects, 2,249 MW
Proposed generation
300 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
982 lb CO2/MWh
Water withdrawals
4.8 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
20,568 employed in construction within ~120 km (32 of 33 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Coles

The sections below set out what public data shows about siting a large electrical load in Coles, Illinois. At 345 kV, Coles carries high-voltage transmission at its strongest mapped point. Coles contains 34 mapped substations, a dense footprint that spreads interconnection options across many points.

Wholesale activity over Coles clears through the MISO market (Midcontinent Independent System Operator), whose footprint sets how interconnection requests and capacity are handled. Coles carries the state industrial average retail rate of 10.1 cents per kWh from EIA-861, applied statewide. For Coles, the per-utility spread is 5 of 6 serving utilities: 1.6 to 15.2¢/kWh, which qualifies but never replaces the state average.

Coles carries 12 projects in the interconnection queue, totalling 2,249.3 MW of requested capacity. In Coles, 300 MW is filed as planned or under construction in the federal EIA-860M inventory. In eGRID, the balancing authority over Coles shows 981.982 lb CO2 per MWh.

For Coles, the USGS 2015 compilation records 4.81 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Coles sits within commuting range of roughly 20,568 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.

Every figure for Coles here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Coles, Illinois settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Coles, Illinois requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Coles, Illinois are logged directly below, so each figure on this page can be traced back to its public dataset.

Sources