Gordon, GA: data center power outlook
Gordon sits in an area outside an organized wholesale market; what follows is the screening-grade grid picture for Gordon, Georgia, drawn from public datasets. Counting from the mapped infrastructure, Gordon holds 20 mapped substations and reaches 500 kV. Gordon is covered by 5 retail service territories, including AMICALOLA ELECTRIC MEMBER CORP, CITY OF CALHOUN - (GA), GEORGIA POWER CO.
Grid position at a glance
- Serving utilities
- AMICALOLA ELECTRIC MEMBER CORP, CITY OF CALHOUN - (GA), GEORGIA POWER CO, NORTH GEORGIA ELEC MEMBER CORP, TENNESSEE VALLEY AUTHORITY
- ISO / market
- NON_ISO (Not in an organized wholesale market)
- Highest grid access
- 500 kV
- Substations in county
- 20
- Industrial retail rate
- 7.8¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 3 of 5 serving utilities: 7.1 to 8.8¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 641 lb CO2/MWh
- Water withdrawals
- 13 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 158,646 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Gordon
Below, Gordon in Georgia is described from public data as a starting point for siting diligence. Gordon reaches 500 kV, a high-voltage transmission class, at its strongest mapped point of grid access. With 20 substations mapped, Gordon has a moderate spread of interconnection points.
Because Gordon, Georgia sits outside an organized market, capacity and interconnection are handled by the utility and bilateral deals, not a market operator. The rate for Gordon is the 7.8 cents per kWh state industrial average (EIA-861), the same figure the map colours by. Across Gordon, reported per-utility industrial rates cover 3 of 5 serving utilities: 7.1 to 8.8¢/kWh, offered only as context beneath the state figure.
No interconnection-queue project is on record for Gordon, Georgia in the covered feeds, which reflects either genuine quiet or a queue not yet ingested. EIA-860M lists nothing planned or under construction for Gordon, Georgia, which is a national filing and so a real zero. The balancing authority covering Gordon carries a grid carbon intensity of 641.018 lb CO2 per MWh in eGRID.
Reported freshwater withdrawals for all uses in Gordon are 13.19 million gallons per day in the USGS 2015 compilation, existing demand rather than water free for a new load. Around Gordon, some 158,646 people work in construction within about a 120 km commute (BLS QCEW), a measure of reach, not of available crews.
These numbers for Gordon are screening-grade context for the whole county, drawn from public data with the gaps left visible. Read the figures for Gordon, Georgia together rather than one at a time: grid access matters less without substations near it, and a quiet queue reads differently inside an organized market than outside one. The next step for Gordon, Georgia is an address-level interconnection study; the county figures here only narrow where to look. For Gordon, Georgia, the source log below records where each figure comes from and when it was pulled, keeping the provenance visible.