Power by county
Glynn, GA: data center power outlook
Glynn, Georgia is served through an area outside an organized wholesale market, and the figures below describe the public grid around a prospective data center site there. Glynn carries 26 mapped substations within its boundary, and the highest reachable grid access is 500 kV. Service in Glynn spans 4 utilities, with COASTAL ELECTRIC MEMBER CORP, GEORGIA POWER CO, OKEFENOKE RURAL EL MEMBER CORP among those mapped.
Grid position at a glance
- Serving utilities
- COASTAL ELECTRIC MEMBER CORP, GEORGIA POWER CO, OKEFENOKE RURAL EL MEMBER CORP, SATILLA RURAL ELEC MEMBER CORPORATION
- ISO / market
- NON_ISO (Not in an organized wholesale market)
- Highest grid access
- 500 kV
- Substations in county
- 26
- Industrial retail rate
- 7.8¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 4 serving utilities: 3.7 to 7.8¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 843 lb CO2/MWh
- Water withdrawals
- 42 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 55,887 employed in construction within ~120 km (17 of 18 counties reporting)A large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Glynn
The material below frames Glynn, Georgia for a prospective large load, drawing only on public sources. Grid access in Glynn extends to 500 kV, a high-voltage line class. The mapped layer packs 26 substations into Glynn, a dense spread of options.
Glynn, Georgia is not inside an organized market, which leaves interconnection to the utility and bilateral contracts. For Glynn, the rate shown is the state industrial average of 7.8 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Glynn that report an industrial rate span 4 serving utilities: 3.7 to 7.8¢/kWh, shown as context and never as the county rate.
Across the covered feeds, Glynn, Georgia carries no interconnection-queue project, from either real quiet or a feed not yet loaded. Nothing is on file for Glynn, Georgia in EIA-860M as planned or under construction, which counts as a measured zero. Glynn sits under a balancing authority that eGRID puts at 842.741 lb CO2 per MWh.
Glynn withdrew 41.82 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 55,887 people are employed in construction within a 120 km commute of Glynn (BLS QCEW), which frames staffing distance rather than free labour.
For Glynn, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Glynn, Georgia describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Glynn, Georgia, a specific address needs its own interconnection study, which this page does not attempt. The figures for Glynn, Georgia refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.