Monroe, FL: data center power outlook

Monroe, Florida is served through an area outside an organized wholesale market, and the figures below describe the public grid around a prospective data center site there. Monroe carries 22 mapped substations within its boundary, and the highest reachable grid access is 138 kV. Service in Monroe spans 4 utilities, with FLORIDA KEYS EL COOP ASSN, INC, FLORIDA POWER & LIGHT CO, LEE COUNTY ELECTRIC COOP, INC among those mapped.

Grid position at a glance

Serving utilities
FLORIDA KEYS EL COOP ASSN, INC, FLORIDA POWER & LIGHT CO, LEE COUNTY ELECTRIC COOP, INC, UTILITY BOARD OF THE CITY OF KEY WEST, F
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
138 kV
Substations in county
22
Industrial retail rate
8.8¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
2 of 4 serving utilities: 8.0 to 12.9¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
597 lb CO2/MWh
Water withdrawals
1.1 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
3,351 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Monroe

The material below frames Monroe, Florida for a prospective large load, drawing only on public sources. At 138 kV, Monroe sits in the transmission class that a large load would look to. The mapped layer packs 22 substations into Monroe, a dense spread of options.

Because Monroe, Florida sits outside an organized market, capacity and interconnection are handled by the utility and bilateral deals, not a market operator. For Monroe, the rate shown is the state industrial average of 8.8 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Monroe that report an industrial rate span 2 of 4 serving utilities: 8.0 to 12.9¢/kWh, shown as context and never as the county rate.

No interconnection-queue project is on record for Monroe, Florida in the covered feeds, which reflects either genuine quiet or a queue not yet ingested. Monroe, Florida has no EIA-860M generation on file, which reads as zero rather than as a gap. Monroe sits under a balancing authority that eGRID puts at 597.091 lb CO2 per MWh.

Monroe withdrew 1.07 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 3,351 people are employed in construction within a 120 km commute of Monroe (BLS QCEW), which frames staffing distance rather than free labour.

For Monroe, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Monroe, Florida describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Monroe, Florida, a specific address needs its own interconnection study, which this page does not attempt. The figures for Monroe, Florida refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.