Martin, FL: data center power outlook

Martin sits in an area outside an organized wholesale market; what follows is the screening-grade grid picture for Martin, Florida, drawn from public datasets. Counting from the mapped infrastructure, Martin holds 18 mapped substations and reaches 500 kV. Martin is covered by 3 retail service territories, including DUKE ENERGY FLORIDA, LLC, FLORIDA POWER & LIGHT CO, GLADES ELECTRIC COOP, INC.

Grid position at a glance

Serving utilities
DUKE ENERGY FLORIDA, LLC, FLORIDA POWER & LIGHT CO, GLADES ELECTRIC COOP, INC
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
500 kV
Substations in county
18
Industrial retail rate
8.8¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 serving utilities: 8.0 to 13.8¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
597 lb CO2/MWh
Water withdrawals
146 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
122,183 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Martin

Everything here about Martin, Florida comes from public federal and state records, with the gaps left visible. Martin reaches 500 kV, a high-voltage transmission class, at its strongest mapped point of grid access. With 18 substations mapped, Martin has a moderate spread of interconnection points.

Martin, Florida is not inside an organized market, which leaves interconnection to the utility and bilateral contracts. The rate for Martin is the 8.8 cents per kWh state industrial average (EIA-861), the same figure the map colours by. Across Martin, reported per-utility industrial rates cover 3 serving utilities: 8.0 to 13.8¢/kWh, offered only as context beneath the state figure.

No interconnection-queue project is on record for Martin, Florida in the covered feeds, which reflects either genuine quiet or a queue not yet ingested. Martin, Florida has no EIA-860M generation on file, which reads as zero rather than as a gap. The balancing authority covering Martin carries a grid carbon intensity of 597.091 lb CO2 per MWh in eGRID.

Reported freshwater withdrawals for all uses in Martin are 145.77 million gallons per day in the USGS 2015 compilation, existing demand rather than water free for a new load. Around Martin, some 122,183 people work in construction within about a 120 km commute (BLS QCEW), a measure of reach, not of available crews.

These numbers for Martin are screening-grade context for the whole county, drawn from public data with the gaps left visible. Read the figures for Martin, Florida together rather than one at a time: grid access matters less without substations near it, and a quiet queue reads differently inside an organized market than outside one. The next step for Martin, Florida is an address-level interconnection study; the county figures here only narrow where to look. For Martin, Florida, the source log below records where each figure comes from and when it was pulled, keeping the provenance visible.