Indian River, Florida is served through an area outside an organized wholesale market, and the figures below describe the public grid around a prospective data center site there. Indian River carries 25 mapped substations within its boundary, and the highest reachable grid access is 500 kV. Service in Indian River spans 4 utilities, with DUKE ENERGY FLORIDA, LLC, FLORIDA POWER & LIGHT CO, PEACE RIVER ELECTRIC COOP, INC among those mapped.
Grid position at a glance
- Serving utilities
- DUKE ENERGY FLORIDA, LLC, FLORIDA POWER & LIGHT CO, PEACE RIVER ELECTRIC COOP, INC, REEDY CREEK IMPROVEMENT DIST
- ISO / market
- NON_ISO (Not in an organized wholesale market)
- Highest grid access
- 500 kV
- Substations in county
- 25
- Industrial retail rate
- 8.8¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 3 of 4 serving utilities: 8.0 to 22.9¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- 75 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 597 lb CO2/MWh
- Water withdrawals
- 63 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 109,900 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Indian River
What follows is a screening-grade read of Indian River, Florida, built only from named public datasets. Grid access in Indian River extends to 500 kV, a high-voltage line class. The mapped layer packs 25 substations into Indian River, a dense spread of options.
Because Indian River, Florida sits outside an organized market, capacity and interconnection are handled by the utility and bilateral deals, not a market operator. For Indian River, the rate shown is the state industrial average of 8.8 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Indian River that report an industrial rate span 3 of 4 serving utilities: 8.0 to 22.9¢/kWh, shown as context and never as the county rate.
The covered queue feeds list nothing for Indian River, Florida, which may be quiet or simply uningested. EIA-860M records 74.5 MW planned or under construction for Indian River. Indian River sits under a balancing authority that eGRID puts at 597.091 lb CO2 per MWh.
Indian River withdrew 63.29 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 109,900 people are employed in construction within a 120 km commute of Indian River (BLS QCEW), which frames staffing distance rather than free labour.
For Indian River, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Indian River, Florida describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Indian River, Florida, a specific address needs its own interconnection study, which this page does not attempt. The figures for Indian River, Florida refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.