Glades, FL: data center power outlook

Glades, Florida is served through an area outside an organized wholesale market, and the figures below describe the public grid around a prospective data center site there. Glades carries 5 mapped substations within its boundary, and the highest reachable grid access is 115 kV. Service in Glades spans 4 utilities, with CITY OF MOORE HAVEN - (FL), DUKE ENERGY FLORIDA, LLC, FLORIDA POWER & LIGHT CO among those mapped.

Grid position at a glance

Serving utilities
CITY OF MOORE HAVEN - (FL), DUKE ENERGY FLORIDA, LLC, FLORIDA POWER & LIGHT CO, GLADES ELECTRIC COOP, INC
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
115 kV
Substations in county
5
Industrial retail rate
8.8¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 of 4 serving utilities: 8.0 to 13.8¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
1,208 lb CO2/MWh
Water withdrawals
133 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
216,696 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Glades

The material below frames Glades, Florida for a prospective large load, drawing only on public sources. At 115 kV, Glades sits in the transmission class that a large load would look to. Glades, Florida carries a thin 5-substation footprint in the mapped layer, concentrating where a connection could land.

Glades, Florida is not inside an organized market, which leaves interconnection to the utility and bilateral contracts. For Glades, the rate shown is the state industrial average of 8.8 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Glades that report an industrial rate span 3 of 4 serving utilities: 8.0 to 13.8¢/kWh, shown as context and never as the county rate.

The covered queue feeds list nothing for Glades, Florida, which may be quiet or simply uningested. EIA-860M lists nothing planned or under construction for Glades, Florida, which is a national filing and so a real zero. Glades sits under a balancing authority that eGRID puts at 1,207.833 lb CO2 per MWh.

Glades withdrew 132.61 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 216,696 people are employed in construction within a 120 km commute of Glades (BLS QCEW), which frames staffing distance rather than free labour.

For Glades, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Glades, Florida describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Glades, Florida, a specific address needs its own interconnection study, which this page does not attempt. The figures for Glades, Florida refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.