Power by county

Lake, CO: data center power outlook

The grid around Lake, Colorado is summarized here from public data, starting from the county's position in an area outside an organized wholesale market. Inside Lake the mapped layer shows 8 mapped substations, with grid access reaching 230 kV at its strongest point. Retail service across Lake is split among 4 utilities, among them CORE ELECTRIC COOPERATIVE, PUBLIC SERVICE CO OF COLORADO, SANGRE DE CRISTO ELEC ASSN INC.

Grid position at a glance

Serving utilities
CORE ELECTRIC COOPERATIVE, PUBLIC SERVICE CO OF COLORADO, SANGRE DE CRISTO ELEC ASSN INC, WAPA-- WESTERN AREA POWER ADMINISTRATION
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
230 kV
Substations in county
8
Industrial retail rate
9.1¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
3 of 4 serving utilities: 2.6 to 9.4¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
None on file (EIA-860M)Units filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
803 lb CO2/MWh
Water withdrawals
23 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
32,518 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Lake

Read on for the public power picture of Lake in Colorado, assembled for data center siting. Transmission-class access reaches 230 kV in Lake at its strongest mapped point. Lake contains 8 mapped substations, a moderate footprint spread across the service area.

No organized wholesale market covers Lake, Colorado, so capacity moves through the local utility and bilateral agreements. Lake carries the state industrial average retail rate of 9.1 cents per kWh from EIA-861, applied statewide. For Lake, the per-utility spread is 3 of 4 serving utilities: 2.6 to 9.4¢/kWh, which qualifies but never replaces the state average.

For Lake, Colorado, no queued project appears in the feeds currently covered. For Lake, Colorado, the EIA-860M inventory shows no planned or under-construction generation, a measured absence. In eGRID, the balancing authority over Lake shows 802.655 lb CO2 per MWh.

For Lake, the USGS 2015 compilation records 22.72 million gallons per day of all-use freshwater withdrawals, not water available to a new load. Lake sits within commuting range of roughly 32,518 construction workers (BLS QCEW, about 120 km), most already committed elsewhere.

Every figure for Lake here is screening-grade and describes the county as a whole, not any single parcel within it. None of the figures for Lake, Colorado settles a site on its own; each one qualifies the others, and all of them come from public federal and state datasets. Settling a site in Lake, Colorado requires a study of the specific parcel, a step beyond the county-level picture drawn here. Sources and data dates for Lake, Colorado are logged directly below, so each figure on this page can be traced back to its public dataset.