Napa, CA: data center power outlook

Napa, California is served through the CAISO market (California Independent System Operator), and the figures below describe the public grid around a prospective data center site there. Napa carries 11 mapped substations within its boundary, and the highest reachable grid access is 230 kV. Service in Napa spans 2 utilities, with PACIFIC GAS & ELECTRIC CO., WAPA-- WESTERN AREA POWER ADMINISTRATION among those mapped.

Grid position at a glance

Serving utilities
PACIFIC GAS & ELECTRIC CO., WAPA-- WESTERN AREA POWER ADMINISTRATION
ISO / market
CAISO (California Independent System Operator)
Highest grid access
230 kV
Substations in county
11
Industrial retail rate
21.6¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
2 serving utilities: 2.9 to 21.1¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
26 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
369 lb CO2/MWh
Water withdrawals
127 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
207,993 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Napa

What follows is a screening-grade read of Napa, California, built only from named public datasets. At 230 kV, Napa sits in the transmission class that a large load would look to. The mapped layer places 11 substations across Napa, a moderate density.

Interconnection over Napa runs through the CAISO market (California Independent System Operator) and its rules. For Napa, the rate shown is the state industrial average of 21.6 cents per kWh (EIA-861), a state figure and not a county-specific one. Beneath that state average, the utilities serving Napa that report an industrial rate span 2 serving utilities: 2.9 to 21.1¢/kWh, shown as context and never as the county rate.

The covered queue feeds list nothing for Napa, California, which may be quiet or simply uningested. EIA-860M records 26.4 MW planned or under construction for Napa. Napa sits under a balancing authority that eGRID puts at 369.346 lb CO2 per MWh.

Napa withdrew 127.22 million gallons per day for all uses in the USGS 2015 data, which counts demand, not headroom. About 207,993 people are employed in construction within a 120 km commute of Napa (BLS QCEW), which frames staffing distance rather than free labour.

For Napa, treat this as screening-grade county context useful for narrowing a search rather than settling a site. Taken together, the figures for Napa, California describe the grid around a prospective site, drawn from public data with their gaps left visible on purpose. To move past screening in Napa, California, a specific address needs its own interconnection study, which this page does not attempt. The figures for Napa, California refresh as their public datasets do, and the exact sources and dates sit in the source log below this section.