Power by county
Monterey, CA: data center power outlook
Monterey sits in the CAISO market (California Independent System Operator); what follows is the screening-grade grid picture for Monterey, California, drawn from public datasets. Counting from the mapped infrastructure, Monterey holds 61 mapped substations and reaches 500 kV. Monterey is covered by 4 retail service territories, including CENTRAL COAST COMMUNITY ENERGY, KINGS RIVER CONSERVATION DIST, PACIFIC GAS & ELECTRIC CO..
Grid position at a glance
- Serving utilities
- CENTRAL COAST COMMUNITY ENERGY, KINGS RIVER CONSERVATION DIST, PACIFIC GAS & ELECTRIC CO., WAPA-- WESTERN AREA POWER ADMINISTRATION
- ISO / market
- CAISO (California Independent System Operator)
- Highest grid access
- 500 kV
- Substations in county
- 61
- Industrial retail rate
- 21.6¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
- Per-utility rates in county
- 3 of 4 serving utilities: 2.9 to 21.1¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
- Interconnection queue
- None on record
- Proposed generation
- 6 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
- Grid carbon intensity
- 369 lb CO2/MWh
- Water withdrawals
- 213 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
- Construction labor near site
- 66,411 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.
Grid conditions in Monterey
Everything here about Monterey, California comes from public federal and state records, with the gaps left visible. Monterey reaches 500 kV, a high-voltage transmission class, at its strongest mapped point of grid access. With 61 substations mapped, Monterey offers interconnection points across many locations.
Monterey falls inside the CAISO market (California Independent System Operator), which governs how its interconnection requests and capacity move. The rate for Monterey is the 21.6 cents per kWh state industrial average (EIA-861), the same figure the map colours by. Across Monterey, reported per-utility industrial rates cover 3 of 4 serving utilities: 2.9 to 21.1¢/kWh, offered only as context beneath the state figure.
The covered queue feeds list nothing for Monterey, California, which may be quiet or simply uningested. Monterey has 6.4 MW of planned or under-construction generation on file in EIA-860M. The balancing authority covering Monterey carries a grid carbon intensity of 369.346 lb CO2 per MWh in eGRID.
Reported freshwater withdrawals for all uses in Monterey are 213.28 million gallons per day in the USGS 2015 compilation, existing demand rather than water free for a new load. Around Monterey, some 66,411 people work in construction within about a 120 km commute (BLS QCEW), a measure of reach, not of available crews.
These numbers for Monterey are screening-grade context for the whole county, drawn from public data with the gaps left visible. Read the figures for Monterey, California together rather than one at a time: grid access matters less without substations near it, and a quiet queue reads differently inside an organized market than outside one. The next step for Monterey, California is an address-level interconnection study; the county figures here only narrow where to look. For Monterey, California, the source log below records where each figure comes from and when it was pulled, keeping the provenance visible.