For Colbert, Alabama, the public grid picture begins with its place in an area outside an organized wholesale market and the infrastructure mapped inside the county. Grid access across Colbert tops out at 500 kV, over a footprint of 37 mapped substations. In Colbert, 7 utilities share the retail territory, among them ALABAMA POWER CO, CITY OF FLORENCE - (AL), CITY OF MUSCLE SHOALS.

Grid position at a glance

Serving utilities
ALABAMA POWER CO, CITY OF FLORENCE - (AL), CITY OF MUSCLE SHOALS, CITY OF TUSCUMBIA, FRANKLIN ELECTRIC COOP - (AL), JOE WHEELER ELEC MEMBER CORP, SHEFFIELD UTILITIES
ISO / market
NON_ISO (Not in an organized wholesale market)
Highest grid access
500 kV
Substations in county
37
Industrial retail rate
7.7¢/kWhState-level EIA-861 industrial average. The map colours by this, not by a per-county rate.
Per-utility rates in county
7 serving utilities: 5.5 to 12.5¢/kWhLowest to highest industrial rate among the utilities serving this county (EIA-861 Sales to Ultimate Customers). A spread, not the county’s rate, and it covers only the serving utilities that report one.
Interconnection queue
None on record
Proposed generation
200 MW planned or under constructionUnits filed with EIA as planned or under construction (Form EIA-860M). Declared intent from the federal inventory, not the interconnection queue and not guaranteed capacity.
Grid carbon intensity
641 lb CO2/MWh
Water withdrawals
1,006 Mgal/dAll uses, freshwater. Water already withdrawn locally, not water available for a new load.
Construction labor near site
29,909 employed in construction within ~120 kmA large build needs hundreds of skilled construction workers on site for one to three years. A county with few of them within commuting range means bussing crews in, per diem, and housing, which is real cost and schedule risk. This counts people employed in construction within about a 120 km drive (BLS QCEW), summed across nearby counties. It is not labor known to be available: most are already committed to other projects, and no public data reveals who is free.

Grid conditions in Colbert

For Colbert, Alabama, the following sections turn public grid records into a siting-oriented summary. The highest mapped voltage in Colbert is 500 kV, in the high-voltage transmission class. Colbert carries 37 substations, a dense footprint across the county.

There is no organized wholesale market over Colbert, Alabama; arrangements run through the serving utility instead. The state industrial average retail rate is 7.7 cents per kWh, drawn from EIA-861 and applied to Colbert at the state level rather than as a county rate. The serving utilities in Colbert that publish a rate range 7 serving utilities: 5.5 to 12.5¢/kWh, a spread kept separate from the state average.

Colbert, Alabama shows no interconnection-queue project in the covered feeds, whether from real quiet or a feed not yet loaded. Federal filings (EIA-860M) list 200 MW of generation as planned or under construction in Colbert. Grid carbon intensity for Colbert, via its balancing authority, is 641.018 lb CO2 per MWh in eGRID.

USGS 2015 puts freshwater withdrawals across Colbert at 1,005.62 million gallons per day for all uses, a measure of use, not spare supply. Within roughly a 120 km commute of Colbert, about 29,909 people are employed in construction (BLS QCEW), which speaks to how far crews for a multi-year build would travel, not to labour known to be free.

Read the Colbert figures as screening-grade context: they describe the surrounding grid, not a specific parcel. The numbers for Colbert, Alabama qualify one another, so grid access, substation density, market membership, and rate are meant to be read as a set, not in isolation. Past this screening view, siting in Colbert, Alabama turns on a study of a particular address, something no county-level page can stand in for. Every number shown for Colbert, Alabama traces to a public source listed below, with its retrieval date, so the provenance is auditable rather than asserted.